BORUSAN EnBW ENERGY
Conducted the required positioning and design studies for
portfolio projects.
Completed the construction and assembly work for the
Balabanlı WEPP (Tekirdağ, 50 MW) and opened the plant for
operation on 11 July 2014. Held the official opening ceremony of
the Balabanlı WEPP on 11 September 2014.
Held groundbreaking ceremonies for the Fuatres WEPP,
Harmanlık WEPP, Mut WEPP and Koru WEPP projects (also on
11 September 2014), and expanded capacity at the currently
operating Bandırma WEPP – all under a 207 MW-wind energy
expansion investment plan formulated in 2013. Started
construction of all these projects. Laid foundations for the
capacity extension of the Bandırma WEPP and the erection of
the Harmanlık WEPP, Mut WEPP and Koru WEPP turbines.
Completed the application process for provisional approval
for the first eight of the nine turbines of the 27 MW-capacity
increase in the 60 MW Bandırma WEPP. Thus, the initial portion
of the Wind Bundle and the Bandırma WEPP Capacity Extension
projects became commercially operational. Raised Bandırma
WEPP’s capacity to 86.4 MW; raised our wind energy installed
capacity to 136.4 MW, and increased our total installed capacity
to 186.4 MW.
Conducted financial negotiations for the Wind Bundle projects.
Hidiv Elektrik Toptan Satış A.Ş. supplied Borusan Group
Companies with electricity in 2014. It continued supplying
electricity to Coca-Cola İçecek A.Ş., its first non-group customer.
Added Borçelik to the Borusan Group sales portfolio.
2014 HIGHLIGHTS
Sectors served
Balancing Power Market
Eligible consumers (industrial and commercial customers that
consume 4,500 kWh/year or more)
CORPORATE INFORMATION
Hydro
Wind
Existing Portfolio (743 MW)
Target Portfolio (2.000 MW)
39%
10%
14%
76%
61%
OPERATIONAL INFORMATION
PARTNER
Hydro
Wind
Other
ENERGY